E&I COMMISSIONING ENGINEER / MANAGER
Specializations:
- Other
Employment: project work
Work schedule: full day, shift schedule, rotation based work
Work experience 26 years 4 months
November 2019 — currently
5 years 8 months
Owner, Private business (Partita IVA).
Technical consultant.
Responsibilities:
Organising and leading of the private business.
Power Analysis and optimisation of the power distribution systems of the Clients in accordance with Standard EN 50160
Solving of the Client’s problems provoked by tension and current harmonics.
Troubleshooting at the Client’s equipment - (Example - diesel generators (up to 1MW) including their protection systems, VFD (variable frequency drive), soft starters etc.)
Improvement and modification of existing automation systems (Example - Aluminium industrial production lines what include motors, encoders, different instruments, VFD, PLC Siemens, HMI panels, different instruments. New PLCs were embedded in the existing systems what highly increased their stability, flexibility and precision)
Writing programs for automation systems (PLC Siemens S7-1200, S7-1500, TIA Portal; WinCC, SCADA (Movicon)). Configuration and Start Up of VFDs Siemens (Sinamics V series, Sinamics G series). Used applications - Starter and TIA Portal+Startdrive. Used communication - analog/digital signals, PROFIBUS, PROFINET.
Projecting, installation and commissioning of the automation systems in accordance with the Clients’ requirements (Example- food production lines what include time, temperature, pressure control, valves, pumps, heating. Realised on Siemens PLC with Siemens HMI panel and PC (WinCC Runtime))
Commissioning/parametrisation of MV VFDs and motors including their auxiliary systems. Example: Client - Siemens Portugal - Project location - Madeira (Calheta), Main equipment - 3 MV VFDs Siemens SINAMICS GM150, P=7.6 MW of each VFD. 3 asynchronous motors, P=5,5MW of each motor.
November 2017 — November 2019
2 years 1 month
Turboden
Italy
E&I Commissioning Engineer
Projects:
Conegliano, Italy
Plock, Poland,
Volos, Greece,
Brescia, Italy,
Brønderslev, Denmark,
Novi Marov, Croatia,
Bjelovar, Croatia (two projects),
Sindal, Denmark,
Vercelli, Italy,
Andijan, Uzbekistan,
etc.
Cold and hot commissioning of ORGANIC RANKINE CYCLE turbogenerators and auxiliary systems.
Responsibilities:
• Commissioning works regarding E&I equipment such as:
1.Cabling (control, LV, MV),
2. 10 kV switchgear,
3. Synchronous and Asynchronous Power Generators,
4. Excitation of synchronous generators,
5. Protection (Sepam 80) and synchronisation (Generator and grid), CTs, VTs
6. 0,4kV power supply, MCC
7.UPS 220V and 0,4kV,
8. Frequency converters (ABB, power up to 250 kW),
9. Electric motors (power up to 250 kW),
10.Pneumatic valves (cut off and regulating), solenoids
11.Instruments (temperature, pressure, level, vibration, flow; leakage detectors) - loop tests, calibration,
12.PLC Simatic S7-400,
• Checking/managing of the current parameters in Step 7 and SCADA.
* Electrical power analysis.
* Alignment of generator/motor with turbine/pump
December 2016 — October 2017
11 months
Libya
LV/MV Electrical Engineer.
GMS of LNG project. Libya, Mellitah.
Relay protection of LV/MV (Sepam) systems.
Responsibilities:
• Assisting to Client in resolving current Electrical Protection problems.
• Preventive and corrective maintenance of LV/MV relay protection systems/electrical equipment.
• Troubleshooting.
• Teaching Electrical staff to Electrical Protection of LV/MV systems
• Solving Engineering issues related to Electrical Protection.
• Systemising of the existing documentation. Preparation of overall data base of all LV/MV electrical consumers, LV/MV power distribution net.
• Implementation of necessary electrical tests.
• Following PTW and LOTO system.
in April, 2017 promoted to position of a Team Leader.
August 2013 — September 2015
2 years 2 months
«Alstom Power» (Power generation and distribution, construction and commissioning of the new power station, France), project in Estonia.
Estonia
Electrical Supervisor
• Management of subcontractors performing electrical installation works.
• Supervising of electrical installation works.
• Assisting subcontractors in resolving current problems.
• Reporting to Engineering about existing issues related to drawings/design.
• Monitoring, verifying and reporting that construction electrical activities comply with the
budget, scope, project schedule.
• Communicating and coordinating of assigned subcontractors activities with other
discipline Superintendents/Supervisors and Construction Manager on daily and weekly
basis.
• Following subcontractors’ activities regarding up-dating of the Athena (Alstom internal
software) data base.
• Following modification («Red Correx», FSI) activity on site issued by Engineering.
• Related equipment and materials management.
• Developing, monitoring, and reporting about completion of subcontractor punch list
activities.
• Leading of the Turn over Inspections of installed electrical equipment with
representatives of Client, Quality and Commissioning department.
• Following PTW and LOTO system.
February 2012 — February 2013
1 year 1 month
«Fortum» (Power generation and distribution, construction of the new power stations), project in Russia. Project: CHELABINSK, Russia. ChGRES. Construction of new CCPP-742,5MW (3 power units-247,5MW), gas-insulated switchgears 220kV, 110kV.
Russia
Manager of electrical installation works
• Participating in daily&weekly meetings with High management&subcontractors.
• Leading of the meetings related to electrical design, installation, commissioning and
maintenance works.
• Technical specifications preparation for new electrical equipment to be purchased and
electrical related works to be executed.
• Tender documentation analysis (Technical part).
• Development of the demolish/construction schedules.
• Electrical design analysis.
• Business trips (inspections, agreement finding) to the factories of the equipment
manufacturers.
• Management of electrical department including design, construction and commissioning
teams.
• Management of subcontractors performing electrical design, installation, commissioning
and maintenance works.
• Assisting subcontractors in resolving current problems.
• Organizing of electrical installation, commissioning and maintenance works.
• Related equipment and materials management.
• Preparation and giving reports to the High management.
• Direct communication with local authority (RosTechNadzor).
February 2011 — February 2012
1 year 1 month
«Enel Ingegneria e generation and distribution, construction, Italy), project in Russia. Project: REFTINSKIY, Russia. Reftinskaya GRES. Construction of new Dry Ash Removal System.
Russia
Electrical Supervisor
• Tender documentation analysis.
• Management of subcontractors performing electrical installation, commissioning and
maintenance works.
• Supervising of electrical installation, commissioning and maintenance works.
• Assisting subcontractors in resolving current problems.
• Reporting to Engineering about existing issues related to drawings/design.
• Monitoring, verifying and reporting that construction electrical activities comply with the
budget, scope, project schedule.
• Communicating and coordinating of assigned subcontractors activities with other
discipline Superintendents/Supervisors and Construction Manager on daily and weekly
basis.
• Related equipment and materials management.
• Organized, followed and made all subcontractors follow the work permit system (PTW,
LOTO) in accordance with Russian legislation - for temporary power distribution net
(MV&LV).
October 2009 — February 2011
1 year 5 months
«Iberdrola» (Power generation and distribution, construction, Spain), project in Russia. Project: SREDNEURALSK, Russia. Sredneuralskaya GRES. Construction of new CCPP-410MW.
Electrical Supervisor
Responsibilities:
• Management of subcontractors performing electrical installation, commissioning and
maintenance works.
• Supervising of electrical installation, commissioning and maintenance works.
• Assisting subcontractors in resolving current problems.
• Reporting to Engineering about existing issues related to drawings/design.
• Monitoring, verifying and reporting that construction electrical activities comply with the
budget, scope, project schedule.
• Communicating and coordinating of assigned subcontractors activities with other
discipline Superintendents/Supervisors and Construction Manager on daily and weekly
basis.
• Following modification («Red Correx», FSI) activity on site issued by Engineering.
• Related equipment and materials management.
• Organized, followed and made all subcontractors (up to 2000 people) follow the work
permit system (PTW, LOTO) in accordance with Russian legislation - for temporary
power distribution net (MV&LV) and for new installed electrical equipment of power
plant.
August 1997 — October 2009
12 years 3 months
SMNU-70/6
Commissioning engineer
Projects:
• NOVOURALSK, Russia. Uranium treatment plant.
• NOVOURALSK, Russia. High speed separators manufacturing plant.
• KIROVGRAD, Russia. Copper-smelting plant. Modification of the water
cooling system for the plant.
• NOVOURALSK, Russia. Power plant. Reconstruction of existing boiler
(100t of steam per hour)
• NOVOURALSK, Russia. Chemical cleaning and hot water supply plant.
• NOVOURALSK, Russia. Batteries manufacturing plant.
Responsibilities:
• Participating in daily&weekly meetings with the Client and Construction
teams.
• Management of electrical commissioning team.
• Analyzing of the electrical design,
• Supervising of electrical installation works,
• Assisting designers and construction teams in resolving current problems.
• Execution of commissioning and startup works.
• Following PTW and LOTO system.
Skills
Skill proficiency levels
About me
Sufficient experience and knowledge in:
• Preparation and issuing of technical specifications.
• Tender documentation analisys.
• Analyzing and mistakes finding in electrical design.
• Installation and commissioning of electrical equipment.
• PTW and LOTO system.
• Materials’ management.
• Coordination of project activities with Client, contractors/subcontractors,
internal departments.
• Supervision of related activities to meet the PM's objectives.
• Providing of required status/reports.
• Excellent inter-personal skills with ability to work effectively as part of a
multi-disciplined international management team.
EQUIPMENT UNDER RESPONSIBILITY
1. HV/MV/LV/DC power distribution systems including:
• HV/MV/LV switchgears, substations,
• power transformers up to 300MVA,
• bus ducts up to 17kV,
• LV busbars,
• batteries,
• cable trays,
• cabling,
• MV, LV, I&C cables’ terminations,
• lightning systems,
• earthing systems,
2. Electric drive including:
• compressors,
• pumps,
• valves,
• HVAC systems,
• electrical inverters,
3. Instrumentation and control systems,
4. Relay protection and automation systems.
5. Lighting systems,
6. Piping heating systems,
7. Eqiupment and cabling for hazardous areas.
Higher education
1997
Moscow State Engineering Physics Institute
Electric drive and automation of industrial facilities and technological complexes, M.S. Degree in Electrical Engineering
Languages
Tests, examinations
2013
Alstom International EHS training
Alstom, Passport is valid up to 30/11/2016
2013
Annual 3 days trainings in Russia regarding organizing and leading of electrical installation, commissioning and maintenance works – 2009/2010/2011/2012.
RosTechNadzor, electrical installation, commissioning and maintenance works
Citizenship, travel time to work
Citizenship: Russia
Permission to work: Italy, Russia
Desired travel time to work: Doesn't matter